I was approached by the design build contractor to find a cost saving solution to bring this multistory, mixed-use residential building closer to their planned budget.

The original design called for post tensioned concrete slabs at every floor.  I found that by redesigning every other floor to be a light gauge cold form steel structure, close to $1.5M in construction and material cost was saved, at zero cost to structural integrity.

Eisen Group

Speak the the nature of the arrangement with Eisen

$1,500,000

Saved in construction costs